Engineering Staff Car Park

Works to install EV infrastructure to a staff parking area, in readiness for the twin 22kW chargers and a 50kW rapid charger. This consisted of;

  • Trenching 35m through slabs and compacted ground

  • Installation of 1 access chamber, 2 EV charge point concrete bases, a feeder pillar base, and an earth pit

  • Laying 110mm and 63mm duct in the trenches

  • Reinstatement of trenches to match existing surface