Electric Truck Company in Essex
Phase 1 was to carry out the groundworks ready to install 5 twin 22kw chargers.
​
-
We cleared foliage and excavated through 25m of compacted ground
-
Excavated and created a concrete base ready for a GRP pillar
-
Laid 163mm ducting in the trench from the feeder pillar to the last charger location
-
Excavated and installed 5 EV Blocks
-
Reinstated all excavations and made good
​
Phase 2 to follow...
​